As of May 2016, the timeline is as follows:

  • Planning application for new school -accepted on 18 May 2016
  • New bridge construction - February ~ December 2016
  • New school construction -September 2016 ~ August  2018

Deadline for pupils moving into new school - August 2018

For enquiries or feedback, please get in touch via the Contact page.